Dutch offshore wind grid connection nears completion at Maasvlakte

The final horizontal drilling operation for TenneT's underground cable route at Maasvlakte, Rotterdam, is underway, marking a critical step toward connecting 6 GW of new offshore wind capacity to the Dutch grid by 2027.

The final horizontal drilling operation for TenneT's underground cable route at Maasvlakte, Rotterdam, is underway...

The last horizontal drilling operation near the Coloradoviaduct on the N15 is now underway. This final drilling completes the installation of underground protective ducts along the cable route between the Amaliahaven high-voltage substation and the converter station for the IJmuiden Ver Beta offshore wind connection.

Contractor NRG is performing this operation. With the ducts now in place, crews will pull the remaining electricity cables through them in early 2027. Patrick Bakelaar, Stakeholder Manager for NRG, stated, "We are now seeing the different parts of the project come together."

Cable installation entering final phase

The onshore works for the Maasvlakte project have entered their final phase. Over the coming months, teams will install the remaining underground cables for three offshore wind connections. Preparations for this final cable installation are already underway at Amaliahaven and the IJmuiden Ver Beta converter station.

Along the several-kilometre route, individual cable sections are being connected in underground chambers known as joint bays. This work forms a continuous link. Once the final cables are installed and connected, the installation work will be largely complete. Contractors will then clear temporary construction sites and restore the surrounding areas.

Project scale and scope

The underground cables will connect three new offshore wind sites to the Dutch grid: IJmuiden Ver Beta, IJmuiden Ver Gamma, and Nederwiek 2. Each connection is designed to bring approximately 2 GW of electricity ashore. Together, they will provide a combined 6 GW of transmission capacity from North Sea wind farms.

ConnectionCapacity
IJmuiden Ver Beta2 GW
IJmuiden Ver Gamma2 GW
Nederwiek 22 GW
Total6 GW

This generating capacity is equivalent to six large gas-fired power stations. Electricity will reach Maasvlakte as direct current and be converted to alternating current by onshore converter stations. From the Amaliahaven substation, power will be transmitted inland and to new grid connections in the Port of Rotterdam.

Contractor and consortium updates

NRG's work on the underground cable connection is scheduled for completion in 2027. The broader offshore grid connections are part of TenneT's 2 GW programme, which aims to deliver thirteen such connections in the Dutch and German North Sea. In 2023, TenneT signed multiyear agreements worth approximately €23 billion for eleven offshore grid connections, each with a capacity of 2 GW.

A consortium comprising GE Vernova and Seatrium holds the contracts for the high-voltage direct-current systems for the IJmuiden Ver Beta, IJmuiden Ver Gamma, and Nederwiek 2 connections. All onshore cables for the three North Sea wind links are projected to be in place by 2027. Remaining underground cables will be pulled through the installed ducts in early 2027, after which temporary work sites will be cleared and surrounding areas reinstated.