Tata Power Renewable Energy Drives Record Q2 FY2027 Results
Tata Power reported a 26% year-on-year revenue surge to ₹19,886 crore in Q2 FY2027, with its renewable energy segment growing to ₹3,746 crore and adding 539 MW of new capacity.

Tata Power delivered record Q2 FY2027 financial results with significant revenue and profit growth across all segments. The company's revenue from operations reached ₹196.36 billion, a 26.3% increase year-over-year. Net profit rose 32.7% to ₹16.52 billion. This performance was supported by a ₹317.36 crore exceptional gain from the derecognition of Tata Projects Limited. Net profit before exceptional items was ₹1,521 crore, up 22% year-on-year. The company achieved its highest-ever quarterly profit after tax of ₹1,652 crore.
Consolidated EBITDA increased 5.3% to ₹42.45 billion. Joint ventures and associates contributed ₹487 crore to profit, a substantial rise from ₹129 crore in the previous year. For the first half of FY 2027, revenue from operations was ₹386.87 billion, up 15.2% from the same period last year.
Renewable Energy Segment Growth
The renewable energy segment demonstrated strong year-on-year growth in revenue, capacity, and electricity sales during Q2 FY2027. Segment revenue grew 3.7% to ₹37.45 billion, while EBITDA for the segment increased to ₹1,728 crore from ₹1,575 crore a year earlier. In the first half of the fiscal year, the segment generated ₹75.17 billion.
Electricity sales from renewable generation jumped 33% year-over-year to 3,329 million units. Operational performance improved markedly. The average solar plant load factor rose to 19.2% from 18%, and the wind plant load factor increased to 37.7% from 30.4%. The rooftop solar business recorded 426 MWp of installations in the quarter, a 15% year-on-year increase.
Capacity Expansion and Infrastructure
Tata Power significantly expanded renewable generation capacity and commissioned key infrastructure projects in Q2 FY2027. The company added 539 MW of generation capacity in the quarter, bringing its total renewable generation capacity to approximately 7.2 GW. This portfolio is composed of specific solar and wind assets.
| Technology | Capacity in Q2 FY2027 | Capacity a Year Earlier |
|---|---|---|
| Solar | 5,825 MW | 4,715 MW |
| Wind | 1,329 MW | 1,030 MW |
During the quarter, the company commissioned 419 MW of utility-scale renewable energy projects. Its broader project pipeline remains robust, with 588 MW of solar and 1,369 MW of hybrid renewable energy projects under construction. An additional 2.8 GW of pumped hydro storage projects are also being built.
Infrastructure milestones included the commissioning of the Jalpura-Khurja transmission corridor, which comprises 164 circuit kilometers of lines and a 1,000 MVA substation. The company's total transmission portfolio now includes 5,724 circuit kilometers of operational lines, with another 2,170 circuit kilometers under construction. In distribution, aggregate technical and commercial losses across Tata Power's Odisha DISCOMs were reduced to 21.0%, an improvement of 5.7% over the previous quarter.
The company's electric vehicle charging network cumulatively installed more than 7,400 public and bus charging points by the end of the quarter. In manufacturing, Tata Power reported approximately 4.9 GW of integrated solar cell and module manufacturing capacity, though module sales declined 19% to 829 MW in the quarter. Solar cell production was 906 MW. The strategic commitment to renewable energy expansion is showed by a record capital expenditure program and a total clean and green energy portfolio, including projects under construction, of approximately 18.3 GW.