Oswal Pumps wins repeat order for 10,000 Maharashtra solar pumps

Oswal Pumps Limited has secured a repeat order worth ₹235.92 crore from MSEDCL to supply and install 10,000 off-grid solar water pumps in Maharashtra under the PM-KUSUM B Scheme.

Oswal Pumps Limited has secured a repeat order worth ₹235.92 crore from MSEDCL to supply and install 10,000 off-grid...

Oswal Pumps has secured a repeat order from the Maharashtra State Electricity Distribution Company Limited (MSEDCL) for 10,000 off-grid DC solar PV water pumping systems. The contract, valued at approximately ₹235.92 crore including GST, was placed on October 30, 2026, under the state's Magel Tyala Saur Krishi Pump Yojana, part of the central PM-KUSUM Component B scheme. The project aims to provide farmers with solar-powered irrigation, reducing dependence on conventional electricity and diesel-based pumping systems.

Oswal Pumps will design, manufacture, supply, transport, install, test, and commission the systems at designated farmers' locations across Maharashtra. Vivek Gupta, Chairman and Managing Director of Oswal Pumps, said securing the repeat contract reflects the confidence placed by MSEDCL in the company’s capabilities and strengthens its existing association with the state utility. The Haryana-based company manufactures submersible pumps, monoblock pumps, electric motors, and solar modules, serving agricultural, residential, and industrial customers.

Technical and operational details

The contract covers the design, manufacture, supply, installation, testing, and commissioning of 10,000 off-grid DC solar photovoltaic water pumping systems. The systems will be available in three different capacities.

Pump Capacity
3 HP
5 HP
7.5 HP

The company will provide complete warranty coverage, repairs, and maintenance services for five years as part of the agreement. A Remote Monitoring System (RMS) will be deployed to monitor the performance and operational status of all pumping installations.

Timeline and execution risk

The entire installation work is scheduled to be completed within 60 days from the date of the work order issuance. This aggressive timeline for the delivery and commissioning of all 10,000 pumps presents a key execution risk. Potential supply chain bottlenecks in procuring solar component sub-assemblies could cause delays.

This fast-track execution window demonstrates Oswal Pumps' deployment capacity in agricultural solar pumps. The order strengthens the company's presence in India's solar irrigation segment and supports renewable energy-based agricultural solutions under government-led programmes. It also expands short-term order book visibility. State electricity distribution companies are increasingly implementing off-grid solar pumps to reduce farm power subsidy burdens and support sustainable irrigation. In September 2026, Oswal Pumps received a Letter of Intent worth ₹273.19 crore from TGREDCO for rooftop solar power systems across 9,937 government schools in Telangana. The full commissioning of the 10,000 solar pumps for MSEDCL is scheduled within a 60-day timeframe.