Morocco launches NOOR PV Multisites solar prequalification for 350 MW

Morocco has opened prequalification for contractors to build its NOOR PV Multisites programme, targeting at least 350 MW of solar capacity across five regions by late 2028, advancing its 2030 renewable energy goals.

Morocco has opened prequalification for contractors to build its NOOR PV Multisites programme, targeting at least 350 MW...

Morocco has launched a recruitment process for contractors to participate in its NOOR PV Multisites solar programme, targeting at least 350 MW of utility-scale solar capacity. The prequalification phase is a key step in the country's push to reach 52 percent renewable electricity by 2030.

The NOOR PV Multisites programme will develop between four and six ground-mounted solar plants with a total capacity of at least 350 MW across five Moroccan regions. The plants will be built in the Casablanca-Settat, Béni Mellal-Khénifra, Marrakech-Safi, Souss-Massa, and Guelmim-Oued Noun regions. Individual project capacities will range from 40 MW to 170 MW. This initiative forms part of Morocco's broader strategy to expand renewable energy deployment and reduce reliance on conventional power generation.

Prequalification process underway

Contractors have until 30 November 2026 to submit prequalification applications under a two-stage competitive process assessing financial and technical capacity. The government adopted the two-stage procurement process to select companies for the programme. In this first stage, interested contractors and consortiums must submit applications for prequalification, where they will be assessed on financial strength, technical expertise, and ability to undertake projects of this scale.

The Request for Qualification notice was published on 14 October 2026. Clarification requests are due by 20 November 2026. Qualified companies will proceed to the second stage to submit detailed technical and commercial proposals. The procurement process covers engineering, procurement and construction, as well as long-term operation and maintenance services.

Timeline for bids and commissioning

Requests for proposals are expected by end-2026 or early 2027, with final bids due in March 2027 and commercial operations slated for late 2028 or early 2029. Authorities expect to issue RFPs in December 2026 or the first quarter of 2027. The deadline for EPC and O&M bids is scheduled for March 2027.

Financial close and construction commencement are tentatively scheduled for the second quarter of 2027. The planned construction period is approximately 18 months. Consequently, the solar facilities could begin commercial operations in the fourth quarter of 2028 or the first quarter of 2029, subject to project execution and commissioning timelines.

Project structure and offtake

A special purpose company backed by Masen will manage EPC and O&M contracts and sign 25- to 30-year power purchase agreements with ONEE. This special purpose company, established by a subsidiary of the Moroccan Agency for Sustainable Energy, will serve as the main contracting entity for the programme. The entity will enter into long-term power purchase agreements with the National Office of Electricity and Drinking Water. These agreements are expected to span 25 to 30 years from the commercial operation date.

Prequalification results are scheduled to be announced on 14 December 2026.