ACME Solar's Q2 FY27 profit surges 134% on BESS and capacity growth
ACME Solar reported a 134% year-on-year jump in Q2 FY27 profit to ₹2.69 billion, driven by a 67.5% rise in total income to ₹10.07 billion.

ACME Solar reported a 133.5% year-on-year increase in consolidated profit after tax to ₹269 crore for the second quarter of FY27. Total income surged 67.5% to ₹1,007 crore, with revenue from operations rising 89.6% to ₹887 crore. The company attributed the revenue growth primarily to additions to its renewable energy and battery energy storage system (BESS) capacities.
Electricity generation rose 19.6% to 1,840 million units during the quarter. The capacity utilization factor improved to 27.8% from 24.1% a year earlier. Plant availability was 99.3%, while grid availability was 99.2%. The company sold 324 million units of electricity through short-term peak power BESS operations in Q2.
Operational Performance and Portfolio
ACME Solar's operational assets are performing strongly. Its Rajasthan solar assets, with 2,281 MW of AC capacity, recorded a capacity utilization factor of 29.6%. Wind assets with 150 MW of contracted capacity achieved an even higher CUF of 41.6%. The company's diversified contracted portfolio now stands at 8.37 GW.
This portfolio breaks down into several key segments:
| Portfolio Segment | Capacity |
|---|---|
| Fully Operational Projects | 2.99 GW |
| Partially Commissioned Projects | 1.92 GW |
| Projects Under Construction | 3.46 GW |
| Total Contracted Portfolio | 8.37 GW |
Fully operational and partially commissioned projects together account for 4.91 GW. During the quarter, ACME signed power purchase agreements for an additional 430 MW of firm and dispatchable renewable energy projects. This took its total signed PPA capacity to 7.3 GW, covering approximately 87% of its contracted portfolio.
BESS Deployment Accelerates
Battery energy storage system deployment was a major highlight. ACME Solar commissioned approximately 2.1 GWh of BESS capacity during the quarter, bringing its cumulative commissioned storage capacity to around 5.24 GWh. This made it the second-largest BESS operator in India by installed capacity. The company has secured contracts with battery suppliers for approximately 19 GWh of storage capacity.
ACME has locked in significant future revenue from its storage business. It reported revenue lock-ins exceeding ₹1,600 crore for partial sales of FY27 BESS capacity and ₹1,500 crore for partial sales of FY28 capacity. The company has also raised its FY27 cumulative BESS commissioning target from 10 GWh to more than 12 GWh.
Financial Metrics and Funding
Consolidated EBITDA increased 63.6% to ₹874 crore, though the EBITDA margin declined to 86.7% from 88.8%. The company attributed this margin decline to the inclusion of power procurement costs associated with BESS operations under operating expenses. Consolidated operating cash flow rose sharply to ₹1,067 crore in the first half of FY27 from ₹294 crore a year earlier.
Substantial investments are being made to support growth. Payments for property, plant and equipment increased to ₹6,329 crore from ₹1,402 crore. To fund this, ACME Solar said it had tied up approximately ₹9,100 crore in debt from a consortium of lenders. The weighted average cost of debt for its fully operational projects stands at 8.4%. Reflecting its strengthened position, the company's credit rating was upgraded to CRISIL AA-/Positive from CRISIL AA-/Stable.
Revised Long-Term Targets
Looking ahead, ACME Solar has significantly raised its long-term capacity targets. The company increased its 2030 renewable energy generation capacity target from 10 GW to 15 GW. It also set a new BESS capacity target of approximately 50 GWh for 2030. For 2032, the targets are even more ambitious: 20 GW of renewable energy generation capacity and approximately 70 GWh of BESS capacity.
These goals reflect a focus on firm and dispatchable renewable energy, assured peak-power supply, and other emerging demand segments. ACME Solar's commitment to achieving its revised 2030 renewable energy capacity target of 15 GW and 50 GWh BESS capacity is supported by the 2.1 GWh BESS capacity commissioned in the latest quarter.