Panamint Capital Closes $769 Million Big Rooter West Solar Financing
Panamint Capital secured $769 million in green financing for the 491 MW Big Rooter West solar project in Texas, the first phase of a $1.8 billion development on reclaimed coal mine land.

Panamint Capital has closed $769 million in financing for the 491 MW Big Rooter West solar project in Texas. This marks the first phase of a $1.8 billion green loan supporting the 1.2 GWdc Big Rooter Power photovoltaic development.
The project is located at the Calvert Mine and Twin Oaks Power Station in Robertson County, roughly midway between Dallas and Houston. It uses reclaimed coal mine land and existing interconnection infrastructure at the 10,000-acre Twin Oaks Complex. The campus combines power generation, surface mining, energy storage, data center capacity, and high voltage transmission. Panamint Capital said, "Big Rooter Power will be the largest brownfield renewable energy project in North America."
Financial close and lender consortium
The $769 million first-phase financing consists of three components. A consortium of three banks acted as coordinating lead arrangers, green loan coordinators, co-syndication agents, and joint bookrunners.
| Financial Component | Amount ($ million) |
|---|---|
| Senior secured construction-to-term loan | 240 |
| Tax equity bridge loan | 461 |
| Letter of credit facility | 68 |
Lloyds, Mitsubishi UFJ Financial Group (MUFG), and Sumitomo Mitsui Banking Corporation (SMBC) served in those coordinating roles. MUFG additionally acted as Administrative Agent across both planned phases of the project.
Legal counsel to Panamint Capital was provided by White & Case and Jackson Walker. Milbank served as legal counsel to the lender consortium. CSC Delaware Trust Company acted as Collateral Agent.
Panamint Capital is a woman-led, US-based energy infrastructure investor headquartered in Incline Village, Nevada. Global Atlantic Financial Group, a wholly owned subsidiary of KKR, holds a minority ownership stake in the firm.
SMBC's Head of Power & New Energies Project Finance, Paul Jun, stated the transaction shows the bank's commitment to supporting clean power projects that deliver critical generation capacity. Panamint Director Tony Shi, who led the deal, said the closing reflects the firm's execution capabilities and capital markets relationships. Competitive terms and robust demand indicate market confidence in the solar facility and in Panamint's structuring ability.
Construction timeline and future phases
Construction of Big Rooter West began in July 2026. Commercial operations are scheduled to start in August 2028.
A second phase, designated for the 658 MWdc Big Rooter East portion of the project, is expected to close in the first quarter of 2027. This phase is valued at over $1 billion. Its targeted commercial operation date is August 2029.
The expected financing structure for Big Rooter East is detailed below.
| Financial Component | Amount ($ million) |
|---|---|
| Construction-to-term loan | 336 |
| Tax equity bridge loan | 587 |
| Letter of credit facility | 91 |
Market context and executive commentary
The deal arrives amid a significant uptick in large-scale solar funding. Announced project financing increased by 75% in the first nine months of 2026 compared to the same period in 2025, according to industry reports.
Panamint Chief Executive Apolka Totth characterized the financing with the three lenders as a strong vote of confidence in the Big Rooter Power project and in Panamint's innovative approach to optimizing America's energy infrastructure. The full 1.2 GWdc project is contracted to a single investment-grade offtaker.
Commercial operations for Big Rooter West are scheduled to begin in August 2028, with the second phase financing for Big Rooter East expected to close in the first quarter of 2027.