Gujarat approves tariffs for 450 MW battery storage projects
The Gujarat Electricity Regulatory Commission has approved tariffs for 450 MW/900 MWh of battery storage projects, enabling development by NLC India Renewables and Sun Drops Energia. The approval provides the legal certainty needed to advance the state's first standalone grid-scale storage infrastructure.

The Gujarat Electricity Regulatory Commission has approved tariffs for 450 MW/900 MWh of battery storage projects, enabling development by NLC India Renewables and Sun Drops Energia. This regulatory green light permits state distribution company GUVNL to execute Battery Energy Storage Purchase Agreements with the two successful bidders. The approval provides the legal and financial certainty for developers and contractors to proceed with critical grid-scale storage infrastructure.
These are the first standalone battery energy storage system installations in Gujarat. They are expected to strengthen grid stability and address the inherent variability of solar and wind energy. The sanctioned capacity shows a robust framework for energy storage. GERC disposed of the petition after granting its approval under provisions of the Electricity Act, 2003.
Competitive bidding determines project allocation
The tariff was set through a competitive bidding process. GUVNL issued a fresh Request for Selection on June 22, 2026. Eleven online bids were received, with ten qualified participants. Nine of those participated in an e-reverse auction held on August 11, 2026.
The process resulted in the following allocations:
| Developer | Capacity Awarded | Tariff per MW |
|---|---|---|
| NLC India Renewables Limited | 275 MW / 550 MWh | ₹231,989 |
| Sun Drops Energia Limited | 175 MW / 350 MWh | ₹231,990 |
Regulatory framework enables project execution
GUVNL filed the petition under Sections 63 and 86(1)(b) of the Electricity Act, 2003. Following the tariff approval, the commission has directed GUVNL to execute the Battery Energy Storage Purchase Agreements within a stipulated timeframe. GUVNL must also submit the executed agreements and publish the detailed tariff structures online.
The projects are supported through Viability Gap Funding under the Power System Development Fund. This Phase IX tender aims to procure significant standalone BESS capacity for peak-load management and ancillary services. A developer under an earlier Phase-VII tender had previously failed to execute an agreement for 900 MWh of capacity.
Projects advance grid stability and renewable obligations
The sanctioned storage capacity directly supports Gujarat's Energy Storage Obligations and Renewable Purchase Obligations. It will aid the integration of solar and wind energy across the state. GUVNL stated that "The proposed battery storage projects will support Gujarat in meeting its Energy Storage Obligations (ESO) and Renewable Purchase Obligations (RPO)."
This infrastructure development supports India's broader renewable energy sector target of 500 GW from non-fossil sources by 2030. Standalone BESS projects require specialized balance-of-plant engineering and high-voltage substation integration. Developers will now clear land acquisition, secure financing, and initiate construction planning to meet commissioning deadlines.